I want to perform different tasks simultaneously on KOMORI PDC-SII

Discussion in 'Komori Printing Presses' started by Vannessa, Mar 11, 2014.

  1. Vannessa

    Vannessa Member

    Joined:
    Mar 2014
    Messages:
    16
    Location:
    Eitobicoke, Canada
    Hello Everyone,

    I am working on the KOMORI PDC-SII so when I select different printing tasks to press, it will select only one at a time. So can anyone please tell me that how can I select more than one tasks to perform simultaneously.
    Thanks in advance
     
  2. Meny

    Meny Senior Member

    Joined:
    Apr 2008
    Messages:
    773
    Location:
    Israel
    What kind of tasks ?

    what do you want to do at the same time ?
     
  3. Vannessa

    Vannessa Member

    Joined:
    Mar 2014
    Messages:
    16
    Location:
    Eitobicoke, Canada
    I want to run different prints on PCQ on same time. When I select on PC then I can select only one but I can not select many prints on same time.
    If you help please.
     
  4. Meny

    Meny Senior Member

    Joined:
    Apr 2008
    Messages:
    773
    Location:
    Israel
    sorry , but i fail to understand your request

    you can only print one job at a time on the press.
    you can only scan and correct one job by closed loop - the job that is on the press.

    what is it that you want to do at the same time ?
    If you add another job to PQC , it will alter the ink keys to suit the plates...but then you need the plates on the press , and you can not have more then one plate /unit a tthe same time.
    So ?
     
  5. Vannessa

    Vannessa Member

    Joined:
    Mar 2014
    Messages:
    16
    Location:
    Eitobicoke, Canada
    Thanks for your response. I mean that I am working on KOMORI PDC-SII and PQC. You know that there is PC on PDC-SII so when I want to select the different printing tasks to start in company's developed software then I can only select one job to start. So my question is that how can I select more than one job to start.
    Sorry to bother you again.
    Thanks in advance.
     
  6. Meny

    Meny Senior Member

    Joined:
    Apr 2008
    Messages:
    773
    Location:
    Israel
    try again :)
    the press can only print that one set of plates at the same time , so no logic in running PDS-S on more then one job at a time.
    what you can do is get as meny jobs as you like ready on KHS-AI / KMS monitor , so the second you finished a job , the next one can go in to PQC memory, PDC-S and so on.
    in fact , on Komori you could set it up to run up to 10 jobs automatically (you only change plates on the hangers) already in 1993 and ever since.

    So , one job only on PDC-S , but as meny as you with in line on the managment system (KHS-AI / KMS4)
    need more help ?
    i could show you haw to do it via remote controll to your press PC over the network.
    then we can also talk on any other questions you may have
    best regards
    Meny
     
  7. Vannessa

    Vannessa Member

    Joined:
    Mar 2014
    Messages:
    16
    Location:
    Eitobicoke, Canada
    [​IMG]
    Hello Meny,
    I am sending you the screen shot of the screen where I want to select more than one job in KMS -> Job Import option.

    So can you please tell me now that how can I do that.

    Regards,
    Vannessa
     
  8. Meny

    Meny Senior Member

    Joined:
    Apr 2008
    Messages:
    773
    Location:
    Israel
  9. Vannessa

    Vannessa Member

    Joined:
    Mar 2014
    Messages:
    16
    Location:
    Eitobicoke, Canada
    Hello Meny, I have sent you the image on your e-mail address. Can you please have a look on it.
     

  10. proslack

    proslack Member

    Joined:
    Sep 2012
    Messages:
    28
    Location:
    Virginia, USA
    You can only have one active job registered at one time.